Train was contracted by TAQA to complete the installation of a new flare stack, water treatment facility and flare system upgrade at the Crossfield Facility. Train was required to do it’s own isometric drawings, purchase materials, qualify, coordinate and manage all 3rd party contractors for this project. Train completed the work in a sour gas facility with no incidents. Most of the work was inside buildings and existing pipe racks which required great diligence when placing pipe and structural steel. This was all done under a very tight schedule. Work consisted of over 14,000 pipe weld inches. Work was coordinated to include a 30 day shutdown with over 110 workers.